Construction project by the numbers.

Hyperion Energy Center estimated cost: $10 billion
The year Hyperion expects construction to begin: 2011.
How long it will take to build the refinery and power plant: 4 years
Number of jobs to be created over the four year construction phase: 4,500
Full time jobs the energy center will create: 1,800